The Long Read · 5 Sep

GE Vernova-class turbine slots still run into 2031

GE Vernova-class slots still run into 2031. A bid in NVIDIA does not buy a turbine.

White gloves, a wafer carrier, and stacked sheets on a clean workbench.
Gloves rest beside a wafer boat and two black stacks.

Thesis map

A GPU this quarter still has to become a watt, a turbine slot into 2031, and a PJM interconnect letter.

Microsoft and Chevron named Kilby at 2.67 gigawatts for 2028. Amazon named GW Ranch in Texas at up to 7.65 gigawatts behind the meter. Those are purchase agreements. GE Vernova-class slots still run into 2031, and PJM docket ER26-3380 still asks a 12 October order that puts a 50-megawatt Large Load without new steel first to curtail.

The chain

  1. 01

    GPU bid

    A hyperscaler can still take a GPU this quarter. One upbeat GPU print with a shrug about turbines does not refute PJM.

  2. 02

    Megawatt

    Microsoft and Chevron named Kilby at 2.67 gigawatts for 2028. Amazon named GW Ranch at up to 7.65 gigawatts behind the meter. Those bargains are energy over a tenor, not an owned plant.

  3. 03

    Turbine slot

    GE Vernova Gas Power equipment backlog and slot reservation agreements grew from 100 to 116 gigawatts. The company anticipates at least 125 gigawatts by year-end 2026. Annual output: 20 gigawatts in Q3 2026, 24 in 2028, actions for 30 in 2030. Slots still run into 2031.

  4. 04

    Interconnect letter

    PJM Interim Resource Adequacy Service, docket ER26-3380, closed comments on 3 September and still asks for a 12 October order. A Large Load of 50 megawatts without newly built dedicated supply is first to curtail. ERCOT large-load requests were 474 gigawatts as of June 2026, from 438 gigawatts on 24 May. That is a request pile, not energised load. PJM still has no ERCOT-style request queue.

Long side

Owns the scarce object. Named filing, named plant, named queue.

GEV

22 July 2026

GE Vernova

116 GW booked, from 100

Data centres are about 20 percent of that book. Averaging GE Vernova with the Utilities ETF is how 2025 plus 0.60 got written and how 2026 minus 0.25 got earned. They are not the same trade. Dominion has about 4 gigawatts of data-centre load in the 2025 peak and 47 gigawatts contracted against a 16.6 gigawatt 2046 forecast.

CEG

owned scan

Constellation

298.96 on 5 September

An ISO auction pays Constellation for the nuclear megawatt to be standing in a delivery year. A dated offtake pays for the energy. Carbon-free certificates ride on the same watt. They do not clear the auction.

VST

7 August 2026, quarter ended 30 June

Vistra

Texas 311 million vs 142 · East 642 vs 418

Ongoing Operations Adjusted EBITDA 1,767 million against 1,349 million. Fleet 19,858 megawatts in Texas and 22,254 megawatts in the East. Hedged about 100 / 94 / 72 percent for 2026 / 2027 / 2028 as of 3 August. That is spark spread and a delivery year, not a model name.

long

groundbreaking 29 June 2026

Hitachi Energy

South Boston 457 million

Hitachi Energy broke ground in South Boston, Virginia, on 29 June 2026, 457 million dollars, completion still 2029. The 17 August Hefei note of 300 million dollars funds bushings and tap changers. It is not a unit on a rail.

NRG

NRG Energy

119.02 on 5 September

NRG printed 119.02 on the 5 September scan. Competitive gas already lives in the auction. A five-day handle is a session. It is not a delivery year.

Short side

Constrained by the chain, or a substitute that is not the product.

NVDA

NVIDIA without a letter

A chip is not a watt. One cautious GPU print with a paragraph about on-site generation is confirmation that Kilby and GW Ranch are now the customer language.

short

Hyperscaler PPA

Kilby and GW Ranch

Kilby at 2.67 gigawatts and GW Ranch at 7.65 gigawatts are purchase agreements. Ownership of generation, built and operated, is still the grade. An oversized contract does not meet that announcement.

short

Utilities sleeve

The Utilities ETF is the rate-base sleeve. GE Vernova is the turbine. Through 21 August the 60-session Pearson of XLU against XLK was minus 0.25. A year earlier the same window printed plus 0.60.

How they interconnect

  • GPU bidstill needsMegawatt

    A GPU bid does not light up until a megawatt is standing at a named delivery point. Kilby and GW Ranch are that language on the offtake page.

  • Megawattneeds aTurbine slot

    The thing that generates the power has a longer lead time than the thing that consumes it. GE Vernova-class slots run into 2031.

  • Turbine slotneeds anInterconnect letter

    A turbine that cannot interconnect is a slide. PJM ER26-3380 writes prove-your-power as a tariff: 50 megawatts without new steel is first to curtail.

  • GE VernovasellsTurbine slot

    GE Vernova booked 116 gigawatts of equipment and slot reservations, from 100, on the 22 July 2026 release. Siemens Energy and Mitsubishi sit on the same lead-time clock. A GPU generation turns over inside that backlog.

  • ConstellationauctionsMegawatt

    Constellation sells nuclear megawatts at auction for a delivery year. Microsoft and Chevron do not own that plant when they name Kilby.

  • VistrasellsMegawatt

    Vistra already lives on energy in Texas and in the East auction. Spark spread is the product. A model name is not.

  • Hitachi EnergygatesInterconnect letter

    A transformer that ships in 2029 gates the interconnect letter a 2026 GPU rack is already waiting on. South Boston completion is still 2029.

  • NRG EnergysellsMegawatt

    NRG is the other independent-power print on the 5 September scan. Competitive gas already sits in the auction. The session is not the delivery year.

  • Interconnect letterblocksNVIDIA without a letter

    An interconnect letter that has not issued leaves NVIDIA with a chip and no watt. The letter constrains the GPU bid, not the other way around.

  • GE VernovaoutrunsNVIDIA without a letter

    A slot booked into 2031 outruns the current NVIDIA cycle. You can buy the chip this quarter. You cannot buy the turbine.

  • Constellationis notHyperscaler PPA

    A purchase agreement is not the nuclear plant. Kilby and GW Ranch pay for energy over a tenor. The auction pays Constellation to be standing.

  • GE Vernovais notUtilities sleeve

    GE Vernova is the turbine. The Utilities sleeve is rate base. Averaging them hid the 2026 split: Energy up 1.66 percent on Friday, Technology down 1.51.

If you believe the thesis

Turbine slots and interconnect letters stay scarce through 2027 while a GPU can still be bought this quarter. Comments on PJM Interim Resource Adequacy Service, docket ER26-3380, closed 3 September. The order they asked for is 12 October. A Large Load of 50 megawatts that skips new steel is first to curtail. Kilby and GW Ranch do not take you off that list until someone owns the plant.

If the thesis is incorrect

The large-load queue in PJM and ERCOT falls for two published updates while hyperscaler capex is still rising. Then silicon was the constraint. Gas-turbine lead times at GE Vernova, Siemens Energy, or Mitsubishi shortening by a year across two consecutive quarters would also print that the bottleneck was temporary.

You can buy a GPU this quarter. You cannot buy a turbine. GE Vernova-class slots run into 2031. Transformer lead times are measured in years. The campus that cannot point to generation does not have a 2027 service date. None of that moves because NVIDIA prints.

You can buy a GPU this quarter. You cannot buy a turbine.

A bid in NVIDIA does not bring the AI trade back. Energy can lead while Technology lags. Utilities can print green while the 10-year rises. That is the watt, not the chip. A name can be bid while the sector sits out. A GPU beat does not buy a turbine slot.

The useful count on the next hyperscaler calls is how often they say constrained, self-generation, behind the meter, and interconnection. One upbeat GPU print with a shrug about turbines does not refute PJM. One cautious GPU print with a paragraph about on-site generation is confirmation that Kilby and GW Ranch are now the customer language.

A GPU can still be bought this quarter. A GE Vernova-class turbine slot still cannot. Transformer lead times still run in years. The useful count on the next hyperscaler calls is how often they say constrained, self-generation, behind the meter, and interconnection. One NVIDIA session does not write that letter.

A GPU print is a name. The interconnect letter is the clock.