Analytics24
3 September
My list

Thesis Maps · 22 Aug

Power is the AI bottleneck

The hall is easy. The interconnect letter and the water permit are the clocks.

A substation and a long hall at first daylight, frost on the grass.
Substation and a hall at first light.
updated 22 Aug 2026

Week of 17–21 August: Utilities (XLU) fell 2.28% on Friday, the worst sector print of the session, and 3.48% on the week. Technology (XLK) closed Friday up 0.11% and lost 3.5% on the week. The ten-year ended four basis points higher at 4.74%, so this was not a duration sell. On the week the two legs of the old AI-power trade fell together. On Friday the selling was utilities-specific. That is owners leaving what had worked. It is not a queue update.

The queue series that is wired is ERCOT: 474 GW of large-load interconnection requests as of June 2026, from the Senate testimony on 29 July, up from 438 GW in the 24 May update. That is a request pile, not energised load. PJM still has no ERCOT-style request queue. Its 2026 long-term load forecast speaks in increments. We will not relabel a forecast increment as a queue. Dominion’s own numbers are the ones that belong on this page: about 4 GW of data-centre load in the 2025 peak, 47 GW contracted against a 16.6 GW 2046 forecast, and a delivery-point queue around 70 GW with 25 GW dated through 2031. The first ratio is how much of the press-release pipeline the utility itself does not believe. The second is how much of the queue has a date.

Prove it with new steel

On 13 August PJM filed Interim Resource Adequacy Service with FERC, docket ER26-3380, and asked for an order by 12 October. A Large Load is 50 MW or more of peak demand at a single site, or affiliated load within one mile. Interim service without newly built dedicated supply means you are first to curtail when the grid is tight. Bring Your Own New Capacity is the valve: designate qualifying new generation for the required duration, or accept a lower quality of service and stay out of everyone else’s capacity price. The 2029/30 demand-curve exclusion is the political twin. When capacity prints above $300 per MW-day, a household in a constrained zone is being asked to fund a reserve margin set by a load the household did not invite. IRAS is a rate case written as a tariff.

Project teams stare at June 2027 service dates. The evidence calendar is earlier. BYONC designations, registry entries, and the first assignment of IRAS responsibility have to exist before the 2027/28 delivery year starts. March–April 2027 is when the paperwork has to be real. FERC’s 12 October clock is the step before that. An order that waters down curtailment priority, or that lets states keep the old socialized capacity treatment, is a different market than the one PJM filed.

GE Vernova-class turbine slots run into 2031. The company has said data centres are about 20% of the book. Transformer lead times are measured in years, often five. You can buy a GPU this quarter. You cannot buy a turbine. Microsoft and Chevron’s Kilby site is 2.67 GW for 2028. Amazon’s GW Ranch in Texas is up to 7.65 GW behind the meter. Those bargains happened in Pecos County, not Loudoun County. Behind-the-meter in northern Virginia is a fight with Dominion, the SCC, and a 70 GW queue. Behind-the-meter in West Texas is a fight with turbines and transformers. Both end at the same sentence: the campus that cannot point to generation is not a 2027 service date.

The claim is the structural claim: before the end of 2027, at least one major hyperscaler announces wholly-owned electricity generation for AI load, built and operated, not a PPA. Purchase agreements, however large, do not count. Ownership does.

What the equities are allowed to say

The claim grades one comparison on 30 November: 60-session correlation of XLU with XLK versus correlation of XLU with the inverse of the ten-year yield change. Live through 21 August that is about −0.25 versus +0.17. Utilities are closer to a rates trade than to Tech on that rule, today. The hypothesis can still win if the ownership returns. It has not returned this month.

The path, not the vibe, is on the utilities insight. 60-session XLU–XLK printed +0.61 in April 2025 and +0.60 in June 2025, the AI-power ownership trade, and is −0.25 now. The 250-session window has come from +0.39 at end-2025 to −0.03. A year of “utilities are tech” is a rounding error on the long window. None of that is a queue update. A correlation path is what the owners did with the stocks.

the next published PJM and ERCOT large-load figures both print above the prior publication. The ERCOT leg grades against 474 GW. The PJM leg waits on a comparable print. Either down is the first of two updates toward kill 01, the bottleneck already rationing demand, and the equity story in power equipment having to live on price and mix. on the Q3 2026 calls, all four of the largest hyperscalers reference power, electricity, or grid capacity as a constraint on deployment. Two or fewer of four, and the constraint has stopped being worth mentioning. NVIDIA on Wednesday night is an input to that count, “constrained,” “self-generation,” “behind-the-meter,” “interconnection”, not a one-night grade.

The kills that are not a stock week

Kill 01: PJM and ERCOT active large-load requests fall for two consecutive official updates while hyperscaler capex guidance is still rising. The queue is clearing faster than demand is added. Kill 02: gas-turbine lead times at GE Vernova, Siemens Energy, or Mitsubishi shorten by 12 months or more across two consecutive quarters. The supply response arrived. Kill 03: aggregate capex guidance of the four largest hyperscalers is cut year-on-year in two consecutive quarters. Demand collapsed; no bottleneck if nobody is building. Theme void, not wrong. Kill 04 is the one that is hardest to see: compute per unit of capability improves so fast that the hyperscalers themselves revise disclosed data-centre megawatt plans down. The electrons were never the constraint; the algorithm was.

Community opposition and labour are the unpriced residual. A tariff can assign curtailment. It cannot site a turbine in a county that does not want one, and it cannot staff a five-year transformer plant that does not yet exist. The prove-your-power calendar has three clocks: the FERC order, the steel, and the neighbours. Only the first one has a docket number.

Henry Hub is a live tile from NYMEX NG=F. Natural gas is a structural demand floor if the campuses get built on gas. Uranium and enrichment stay pending rather than spammed. The chips arrive on the buyer’s clock. The electrons arrive on the supplier’s. This week’s XLU print did not change either clock.

Rate base is not the same trade as the turbine

If the queue is the moat, incumbent colocation with an existing interconnect and utilities with load growth in-territory get pricing power on power. That is a rate-case story. If turbines are the bottleneck, GE Vernova, Siemens Energy, and Mitsubishi get backlog and price, and the equity that owns them is not XLU. If hyperscalers become generators, capex mix shifts from servers to plant and the independent power producer, the gas developer, and the nuclear restart file get the bid. Those three if-thens can print in the same year and pull XLU, GEV, and a hyperscaler in three directions. Averaging them into “AI power” is how 2025’s +0.60 correlation got written. It is also how 2026’s −0.25 got earned.

Regulators decide who pays for the interconnect. State utility-commission dockets are not a series. They are a risk to the “utilities win” leg. A world where large-load tariffs shove the cost onto the campus is a world where the regulated equity’s upside is smaller than the 2025 ownership assumed. IRAS is that shove, written as a federal tariff. Watch the 12 October order for whether FERC lets it stand.

Efficiency is the quiet kill

Kill 04, hyperscalers revising MW plans down because compute-per-watt improved, will not arrive as a victory lap. It will arrive as a sentence in a 10-K that everyone will call “discipline.” Named here so a down-guide on megawatts cannot be recast later as “we never thought power was the constraint.” Until that sentence appears, treat every “AI demand” headline that ignores prove-your-power calendars as a GPU press release.

NVIDIA’s Wednesday commentary is a count, not a grade. How often “constrained,” “self-generation,” and “interconnection” show up feeds. One upbeat GPU print with a shrug about turbines is not a refutation of PJM. One cautious GPU print with a paragraph about on-site generation is confirmation that Kilby and GW Ranch are now the customer’s language, not just the ISO’s.

Nothing structural changed this week. The stocks moved. Write it that way.